Lack of washing pit lines
blocking the lines article is in CSR
Competition success magazine Each
train is needed to be washed between two consecutive journeys. This
means that the number of washing pit lines must be adequate to maintain
urgency. However,
Competition success magazine the number of
washing pits is much below the requirement. Stabling lines are vacant lines wherein the empty trains are parked after their
arrival as they wait for their turn to
proceed
competition success review to the washing lines. The
CAG report considered 79 pit lines along with 63 stabling lines and
found that only 24 stabling lines and 35 pit lines have the required capacity
needed for handling 24 coaches or more. competition success review
All of this leads to delay in the departure of trains and
eventually their arrival.